TIMMONS GROUP YOUR VISION ACHIEVED THROUGH OURS. Chicago Avenue/Waterman Drive Offset Intersection (WB-62) Preliminary Planning Cost Estimate - March 2025 City of Harrisonburg, Virginia
(Input Length of Roadway, (FT)) Facility Classification
Offset Intersection
Designed for WB-62
CONSTRUCTION BID COSTS
Grading & Earthwork $ 47,000.00
Roadway Improvements $ 232,000.00
Stormwater & Hydraulics 70% $ 196,000.00
Miscellaneous Construction 30% $ 143,000.00
Subtotal A = $ 618,000.00
OTHER BID COSTS FOR CONSTRUCTION
Mobilization for Subtotal A (Calc from VDOT formula) $ 52,000.00
Construction Surveying 1.5% $ 10,000.00
Materials Testing 2% $ 13,000.00
Construction Engineering & Inspection 20% $ 139,000.00
Contingency for CN (Construction + Other) 50% $ 416,000.00
Subtotal B = $ 630,000.00
TOTAL ROADWAY CONSTRUCTION ITEMS (A + B): $ 1,248,000.00
PRELIMINARY ENGINEERING (DESIGN & ADMINISTRATIVE COSTS)
Survey, Design Services, & Permitting 20% $ 250,000.00
Environmental Coordination 0% -
Contingency for PE 10% $ 25,000.00
Subtotal C = $ 275,000.00
GRAND TOTAL ROADWAY ITEMS (A+B+C): $ 1,523,000.00
RIGHT OF WAY & UTILITY COSTS
Utility Coordination & Relocation 15% $ 229,000.00
Right of Way - Administrative Costs $ 20,000.00
Right of Way - Acquisition Costs $ 41,000.00
Contingency for Right of Way/Utility 50% $ 145,000.00
ROW Subtotal = $ 435,000.00
SUMMARY OF BUDGET PHASES
Preliminary Engineering (PE) $ 275,000.00
Right of Way (RW) $ 435,000.00
Construction (CN) $ 1,248,000.00
TOTAL RECOMMENDED PROJECT BUDGET $ 1,958,000.00