City of Harrisonburg W Market Street Crossing & Quarry Heights Connection Preliminary Planning Cost Estimate - March 2025 Image
City of Harrisonburg, Virginia
(Input Length of Roadway, (FT)) Facility ClassificationSignalized Ped Crossing + Shared Use Path
CONSTRUCTION BID COSTS
Grading & Earthwork$ 16,000.00
Roadway Improvements$ 153,000.00
Stormwater & Hydraulics20%$ 34,000.00
Miscellaneous Construction20%$ 41,000.00
Subtotal A = $ 244,000.00
OTHER BID COSTS FOR CONSTRUCTION
Mobilization for Subtotal A (Calc from VDOT formula)$ 24,000.00
Construction Surveying1.5%$ 4,000.00
Materials Testing2%$ 5,000.00
Construction Engineering & Inspection15%$ 42,000.00
Contingency for CN (Construction + Other)50%$ 160,000.00
Subtotal B = $ 235,000.00
TOTAL ROADWAY CONSTRUCTION ITEMS (A + B):$ 479,000.00
PRELIMINARY ENGINEERING (DESIGN & ADMINISTRATIVE COSTS)
Survey, Design Services, & Permitting15%$ 72,000.00
Environmental Coordination0%-
Contingency for PE10%$ 8,000.00
Subtotal C = $ 80,000.00
GRAND TOTAL ROADWAY ITEMS (A+B+C):$ 559,000.00
RIGHT OF WAY & UTILITY COSTS
Utility Coordination & Relocation15%$ 84,000.00
Right of Way - Administrative Costs
Right of Way - Acquisition Costs
Contingency for Right of Way/Utility50%$ 42,000.00
ROW Subtotal = $ 126,000.00
SUMMARY OF BUDGET PHASES
Preliminary Engineering (PE)$ 80,000.00
Right of Way (RW)$ 126,000.00
Construction (CN)$ 479,000.00
TOTAL RECOMMENDED PROJECT BUDGET$ 685,000.00