City of Harrisonburg Chicago Avenue Corridor Phase 1 (SB) Greystone Street to Rockingham Drive YOUR VISION ACHIEVED THROUGH OURS. Preliminary Planning Cost Estimate - March 2025 City of Harrisonburg, Virginia
(Input Length of Roadway, (FT)) Facility Classification
C&G + Shared-Use Path
CONSTRUCTION BID COSTS
Grading & Earthwork $ 25,000.00
Roadway Improvements $ 151,000.00
Stormwater & Hydraulics $ 88,000.00
Miscellaneous Construction $ 53,000.00
Subtotal A = $ 317,000.00
OTHER BID COSTS FOR CONSTRUCTION
Mobilization for Subtotal A (Calc from VDOT formula) $ 29,000.00
Materials Testing $ 7,000.00
Construction Engineering & Inspection $ 54,000.00
Contingency for CN (Construction + Other) $ 206,000.00
Subtotal B = $ 301,000.00
TOTAL ROADWAY CONSTRUCTION ITEMS (A + B): $ 618,000.00
PRELIMINARY ENGINEERING (DESIGN & ADMINISTRATIVE COSTS)
Survey, Design Services, & Permitting $ 124,000.00
Construction Surveying $ 5,000.00
Environmental Coordination $ -
Contingency for PE $ 13,000.00
Subtotal C = $ 137,000.00
GRAND TOTAL ROADWAY ITEMS (A+B+C): $ 755,000.00
RIGHT OF WAY & UTILITY COSTS
Utility Coordination & Relocation $ 114,000.00
Right of Way - Administrative Costs $ 30,000.00
Right of Way - Acquisition Costs $ 78,000.00
Contingency for Right of Way/Utility $ 111,000.00
ROW Subtotal = $ 333,000.00
SUMMARY OF BUDGET PHASES
Right of Way (RW) $ 333,000.00
Construction (CN) $ 618,000.00
TOTAL RECOMMENDED PROJECT BUDGET $ 1,088,000.00
Preliminary Engineering (PE) $ 137,000.00