City of Harrisonburg Chicago Avenue Corridor Phase 2 (NB) Shenandoah Street to Waterman Drive YOUR VISION ACHIEVED THROUGH OURS. Preliminary Planning Cost Estimate - March 2025 City of Harrisonburg, Virginia
(Input Length of Roadway, (FT)) Facility Classification
C&G + Sidewalk
CONSTRUCTION BID COSTS
Grading & Earthwork $ 134,000.00
Roadway Improvements $ 229,000.00
Stormwater & Hydraulics $ 182,000.00
Miscellaneous Construction $ 109,000.00
Subtotal A = $ 654,000.00
OTHER BID COSTS FOR CONSTRUCTION
Mobilization for Subtotal A (Calc from VDOT formula) $ 55,000.00
Materials Testing $ 14,000.00
Construction Engineering & Inspection $ 74,000.00
Contingency for CN (Construction + Other) $ 404,000.00
Subtotal B = $ 557,000.00
TOTAL ROADWAY CONSTRUCTION ITEMS (A + B): $ 1,211,000.00
PRELIMINARY ENGINEERING (DESIGN & ADMINISTRATIVE COSTS)
Survey, Design Services, & Permitting $ 243,000.00
Construction Surveying $ 10,000.00
Environmental Coordination $ -
Contingency for PE $ 25,000.00
Subtotal C = $ 268,000.00
GRAND TOTAL ROADWAY ITEMS (A+B+C): $ 1,479,000.00
RIGHT OF WAY & UTILITY COSTS
Utility Coordination & Relocation $ 222,000.00
Right of Way - Administrative Costs $ 110,000.00
Right of Way - Acquisition Costs $ 369,000.00
Contingency for Right of Way/Utility $ 351,000.00
ROW Subtotal = $ 1,052,000.00
SUMMARY OF BUDGET PHASES
Right of Way (RW) $ 1,052,000.00
Construction (CN) $ 1,211,000.00
TOTAL RECOMMENDED PROJECT BUDGET $ 2,531,000.00
Preliminary Engineering (PE) $ 268,000.00