EXPENDITURES BY UNIT

Bond Funded Construction8,148,4283,161,809335,717,400
State Funded Construction433,193,364413,087,1741,237,140,900436,889,100460,667,900
Federal Funded Construction1,315,008,6291,159,553,4613,090,313,0001,454,428,6001,466,049,000
TOTAL EXPENDITURES1,756,350,4211,575,802,4444,663,171,3001,891,317,7001,926,716,900

In the Construction program is the largest single funding component within the Highways appropriation unit. It encompasses all construction and major reconstruction of roadways in the State Primary Road System. The Construction Program is divided into five sub-programs: Bond Funded Construction, State Funded Construction, Federal Funded Construction, Toll Bond Funded Construction, and the TIFIA Loan program. KRS 45.750(3) exempts road projects, including associated equipment and land acquisition purchases, from the capital construction statutes outlined in KRS Chapter 45.760 - 45.810.

Several different road systems constructed in the Commonwealth over the last 40 years have used Bond Funded Construction. General obligation bonds were sold to finance the original construction of the Interstate System. The Turnpike Authority of Kentucky sold revenue bonds to fund construction of the toll road system that crisscrosses the state. Tolls on these parkways were removed once the bonds were paid. Resource recovery bonds were sold in the late 1970s for construction of the Resource Recovery Road System, a network of highways over which coal resources could be efficiently hauled. The Turnpike Authority received authorization to sell bonds in 1984, 1987, 1990, 1993, 1995, 1999, 2005, 2006, 2008, 2009, and 2010 for projects identified as part of the Economic Development Road System. The Authority received authorization in 2008 and 2010 to issue bonds to support road projects specifically related to the Base Re-alignment and Closure (BRAC) activities in and around Fort Knox. All of the roads constructed using proceeds from Turnpike Authority bonds are built by the Cabinet on behalf of the Authority, and then are leased to the Cabinet until the bonds are retired. At that time they are transferred to the Cabinet and become a part of the state highway system.

The State Funded Construction program provides for many highway improvement needs, emergency needs, industrial access roads, parkway and primary road pavement rehabilitation, and other projects for which federal funding is not available. The state resurfacing program is a part of this sub-program area and provides for resurfacing of roads in the state maintained highway system. The Highway Construction Contingency account, authorized in KRS 45.247, is also included in the State-Funded Construction program.

The Federal Construction program addresses the major construction, reconstruction, and rehabilitation needs for nearly 12,000 miles of interstate, primary, secondary, urban systems, and Appalachian routes across the state. This funding is provided under Titles 23 and 40 of the US Code. From fiscal year 2005 to fiscal year 2008, $440 million in Grant Anticipation Revenue Vehicle (GARVEE) bonds were appropriated to support interstate projects along I-64, I-75, and I-65. In addition, GARVEE bonds totaling $336 million were authorized in 2008 and 2010 for the Louisville Bridges project. The 2010 Special Session of the General Assembly authorized $330 million in GARVEE bonds for the US-68/KY-80 Lake Barkley and Kentucky Lake Bridges Project. For display purposes, the GARVEE bonds are located in the Bond Funded Construction program. However, the debt service to support the GARVEE bonds is located in the Federal Fund Construction program.

House Bill 4 from the 2009 Special Session of the General Assembly created the Kentucky Public Transportation Infrastructure Authority (KPTIA) to facilitate the construction, financing, operation, and oversight of mega-projects. According to the Federal Highway Administration, mega-projects are projects that have a total cost of $500 million or more. The Authority has the power to finance mega-projects through the use of tolls, funds from any GARVEE, funds appropriated by the state or federal government, and any other funds pledged for their purpose. House Bill 241 from the 2022 Regular Session of the General Assembly approved $150 million in GARVEE Bond Funds to be issued for the Brent Spence Bridge Project. House Bill 265 from the 2024 Regular Session of the General Assembly approved $150 million in GARVEE Bond funds to be issued for the I-69 Ohio River Crossing Project.

Policy

The budget authorizes the Secretary of Transportation to continue the Cash Management program, formerly known as the Pre-financing Road Projects program, authorized by the Appropriations Act since the 2000-2002 biennium. The Cash Management program allows the Cabinet to expedite projects in the Biennial Highway Construction Plan by managing Road Fund cash, while ensuring that expenditures remain within enacted appropriations.

Included in the State Supported Construction Program is $20,000,000 in each fiscal year from the Road Fund for the County Priority Projects Program and $25,000,000 in each fiscal year from the Road Fund for the County Bridge Improvement program. Both of these programs were new in the 2024-26 biennial budget.

373