S.R. 789 from Bird Key Drive to Sunset Drive: Construction project: This project includes the addition of dedicated bicycle and transit lanes on the bridge, drainage upgrades, and raising the seawall cap near Sunset Drive. Other project activities include resurfacing the roadway throughout the project corridor and the installation of new traffic signals at the intersections of Sunset Drive, Golden Gate Drive, and Bird Key Drive. The project also includes relocating palm trees and small shrubs from their current locations on the eastern area of the John Ringling Causeway to medians closer to St. Armands Circle.
Sunset Drive will be temporarily closed at the Ritz entrance off Gulfstream Avenue (S.R. 789) to accommodate driveway reconstruction and related roadway improvements. The closure is anticipated to remain in place for approximately 60 days. Please follow posted detours, traffic-control devices, and directions from construction personnel.
This week's work will consist of:
Delivering machinery and materials as needed.
Installing concrete curb and sidewalk along the north side of the Sunset Drive intersection.
Installing drainage pipes and structures along the north side of Bird Key Drive, then transitioning to the south side of Sunset Drive.
Installing pull boxes and wiring for traffic signals at the Sunset Drive and Bird Key Drive intersections.
Installing traffic signal mast arms at the Bird Key Drive intersection.
Removing existing mast arm drilled shafts at the Sunset Drive intersection.
Installing pull boxes and wiring for roadway lighting along both sides of the road throughout the project limits.
Preparing to begin seawall cap replacement along the south side of the roadway, east of Golden Gate Point.
Preparing to begin roadway widening along the south side of Sunset Drive.
Milling and paving operations will resume at a later date.
Pedestrians should use designated paths and follow posted detour signs. Bike lanes are closed due to construction. Cyclists should follow the posted detour.