Anticipated completion is late 2026.
S.R. 17 from C.R. 17 (Kenilworth Boulevard) to East of U.S. 98/U.S. 27 and from South of Lake Verona Boulevard to South Delaney Avenue: Construction project: Crews are beginning roadway improvements along S.R. 17 in Highlands County. The project includes milling and resurfacing, drainage improvements, sidewalk and curb upgrades, signalization and lighting enhancements, railroad crossing reconstruction, and new signage and pavement markings.
Intermittent daytime lane and shoulder closures will occur Monday through Friday from 7 a.m. to 5 p.m., as needed, throughout the project limits for intersection and pedestrian improvements.
Beginning Monday, November 2, 2026, crews will perform nighttime milling and paving operations on S.R. 17 from Kenilworth Boulevard to Sebring Parkway. Motorists should expect intermittent lane closures, possible traffic delays, and construction equipment in the work zone while this work is underway.
Parking along S.R. 17 near Sebring Circle will be limited during paving operations. Motorists, residents, and visitors should plan their travel and parking arrangements accordingly and allow additional travel time.
After nighttime paving operations progress through the Kenilworth Boulevard to Sebring Parkway section, paving operations will transition to daytime hours from Sebring Parkway to Main Street in the City of Avon Park.
Crews will continue sidewalk, curb, lighting, pedestrian pole, and pull-box installation work at various intersections.
Overnight construction is scheduled at S.R. 17 (Main Street) and North Lake Avenue in October, 2026, weather permitting. Work will include signalization improvements, directional boring, and pull-box installation.
Pedestrian access near active work areas may be temporarily closed. Pedestrians should plan accordingly, follow posted signs, and use designated temporary pedestrian detours.
Motorists should expect workers, construction equipment, and possible changes in traffic patterns near the North Pine Street intersection. Drivers should use caution and follow all posted signs and directions from flaggers.
Motorists should remain alert and watch for workers and equipment throughout the construction zone.
Estimated completion is in summer 2027.