PURCHASING POLICY
APPENDIX D Procurement Lead Time
NUMBER: 06-02
SAMPLE LEAD TIME FOR A COMPLEX PROJECT
TaskSuggested Lead Time from Start of Contract DateExample
Begin Preparation of Specification and contract.180 daysMarch 1
Final approval of Specifications150 daysApril 1
Advertise and Issue Solicitation (Bid/RFP/RFQ)120 daysMay 1
Receipt of Responses90 daysJune 1
Evaluation of Responses5 – 30 daysJuly 1
Contract Negotiation30 daysAugust 1
Council Award10 daysAugust 10
Contract Execution - City3-10 daysAugust 20
Contract Execution / BondingMinimum 10 daysAugust 30
Contract BeginsSeptember 1