that detours via US 41 Business (Green Bridge) instead of US 41 and the DeSoto Bridge could result in additional travel times ranging from approximately 12 to 30 minutes, depending on the time of day.
It is anticipated that top-down construction techniques will be utilized for the elevated viaduct structure in order to minimize the total width of the required median work zones. Traffic can be shifted as necessary away from the median area while maintaining the flow of traffic.
Traffic shifts and temporary pavement, with overbuild, will be utilized to construct and maintain landside traffic patterns. Construction of the shared use paths and sidewalks will be incorporated in the phasing plans.
Construction of the Build Alternative is expected to have moderate impacts related to property access. Construction is not anticipated to adversely impact listed species so long as adherence to project commitments, construction precautions, and conservation measures is maintained. Also, construction is not expected to have any significant impact on water quality, noise, or air quality. The project will adhere to the FDOT Standard Specifications for Road and Bridge Construction, along with implementing a Stormwater Runoff Control Concept and Best Management Practices to minimize or eliminate potential construction impacts.
Page | 84