Table 5-3 – Alternative Evaluation Matrix

BRADENTON-PALMETTO CONNECTOR PD&E STUDY
Evaluation CriteriaNo-BuildPreferred AlternativeInterim Improvements
No Improvements4 lanes Added (2L at-grade and 2L Elevated)2 lanes Added (2L at-grade from S.R. 64 to U.S. 301)
Ability to meet Purpose and Need
CapacityImageImageImage
Transportation Demand
Safety
Potential Right of Way Impacts
Parcels (# Business | # Residential | # Other )-38 | 43 | 178 | 0 | 2
Area of Impact (acres)-27.34.4
Residential Relocations (# )-60
Business Relocations (# )-10
Utilities (Yes, No)-YesYes
Environmental Impacts
Protected Species (Low, Moderate, High)-ModerateModerate
Contamination Risk Sites (#) (Medium | High)-30 | 16 | 2
Wetland (acres)-1.81.2
Seagrass (acres)-00
Surface Water (Low, Moderate, High)-ModerateModerate
Section 4(f) Resources (# )-43
Archaeological & Historic Resources (# )-42
Noise-Sensitive Receptors (#) (Evaluated | Impacted)-1,128 | 341244 | 72
Estimated Project Costs (2026 $)*
Right of Way Estimate ($ )*$0$ 45.0 M$ 15.0 M
Design ($ ))*$0$ 73.2 M$ 22.1 M
Construction ($ ))*$0$ 732.1 M$ 220.5 M
Construction Engineering & Inspection (CEI) ($ )*$0$ 73.2 M$ 22.1 M
Preliminary Estimate of Total Project Cost ($ )*$0$ 923.5 M$ 279.7 M
* ALL COSTS AND VALUES ARE PRELIMINARY AND SUBJECT TO CHANGE

Page | 62