FDOT Long Range Estimating System - Production R3: Project Details by Sequence Report

Project: 442630-2-52-01

Letting Date: 07/2030

Description: DESOTO (US 41) BRIDGE FROM NORTH OF SR 64 TO HABEN BLVD BRIDGE #130053

District: 01 County: 13 MANATEE Market Area: 10 Units: English

Market Area: 10 Units: English

Contract Class: 9 Lump Sum Project: N Design/Build: Y Project Length: 5.242 MI

Design/Build: Y Project Length: 5.242 MI

Project Manager: NEM-BCC-JLM

Version 21 Project Grand Total

Description: March 2026 Markups from Version 20-3/31/26

$200,612,900.30

Project Sequences Subtotal $144,062,450.81

102-1 Maintenance of Traffic 15.00 % $21,609,367.62

101-1 Mobilization 10.00 % $16,567,181.84

Project Sequences Total $182,239,000.27

Project Unknowns 10.00 % $18,223,900.03

Design/Build 0.00 % $0.00

Non-Bid Components:

Pay item Description Quantity Unit Unit Price Extended Amount

999-25 INITIAL CONTINGENCY AMOUNT (DO NOT BID) LS $150,000.00 $150,000.00

Project Non-Bid Subtotal $150,000.00

Version 21 Project Grand Total $200,612,900.30

$200,612,900.30

Version 21 Project Grand Total