Date: 4/3/2026 9:15:39 AM
FDOT Long Range Estimating System - Production R3: Project Details by Sequence Report
Project: 442630-2-52-01
Letting Date: 07/2030
Description: DESOTO (US 41) BRIDGE FROM NORTH OF SR 64 TO HABEN BLVD BRIDGE #130053
District: 01 County: 13 MANATEE Market Area: 10 Units: English
Market Area: 10 Units: English
Contract Class: 9 Lump Sum Project: N Design/Build: Y Project Length: 5.242 MI
Design/Build: Y Project Length: 5.242 MI
Project Manager: NEM-BCC-JLM
Version 21 Project Grand Total
Description: March 2026 Markups from Version 20-3/31/26
$200,612,900.30
Project Sequences Subtotal $144,062,450.81
102-1 Maintenance of Traffic 15.00 % $21,609,367.62
101-1 Mobilization 10.00 % $16,567,181.84
Project Sequences Total $182,239,000.27
Project Unknowns 10.00 % $18,223,900.03
Design/Build 0.00 % $0.00
Non-Bid Components:
Pay item Description Quantity Unit Unit Price Extended Amount
999-25 INITIAL CONTINGENCY AMOUNT (DO NOT BID) LS $150,000.00 $150,000.00
Project Non-Bid Subtotal $150,000.00
Version 21 Project Grand Total $200,612,900.30
$200,612,900.30
Version 21 Project Grand Total