Date: 3/31/2026 11:33:45 AM
FDOT Long Range Estimating System - Production R3: Project Details by Sequence Report
Project: 444843-1-22-01 Letting Date: 01/2099
Description: US 41/SR 55 from US 301/SR63 at 9th Street East to north of 25th Street East
District: 01 County: 13 MANATEE Market Area: 10 Units: English
Contract Class: 4 Lump Sum Project: N Design/Build: N Project Length: 4.512 MI
Project Manager: NEM-AEH-SAA
Version 2 Project Grand Total $732,268,758.02
Description: March 2026 GFT Markups from Version 1-3/24/26
Project Sequences Subtotal $463,000,005.08
102-1 Maintenance of Traffic 15.00 % $69,450,000.76
101-1 Mobilization 10.00 % $53,245,000.58
Project Sequences Total $585,695,006.42
Project Unknowns 25.00 % $146,423,751.60
Design/Build 0.00 % $0.00
Non-Bid Components:
Pay item Description Quantity Unit Unit Price Extended Amount
999-25 INITIAL CONTINGENCY AMOUNT (DO NOT BID) LS $150,000.00 $150,000.00
Project Non-Bid Subtotal $150,000.00
Version 2 Project Grand Total $732,268,758.02