# US 19 Repaving from South of Tampa Road to South of Live Oak Street 451287-1-52-01
| Project Details |
| Work Type | Repaving |
| Phase | Completed |
| Limits | from south of Tampa Road to south of Live Oak Street |
| Project Start | January 5, 2026 |
| Length | 6 Miles |
| City | Palm Harbor Tarpon Springs |
| County | Pinellas |
| Road | US 19 |
| Construction Cost | $8.5 million |
| Estimated Completion | Fall 2026 |
| Contractor | Preferred Materials, Inc. |
| Contact Information |
| Project Information |
| Maddie Griffin\n(727) 575-8334 | Maddie.Griffin@dot.state.fl.us |
| Media Contact |
| Kayla Mejia\n813-975-6060 | Kayla.Mejia@dot.state.fl.us |
Map data ©2026 Google, INEGI
## About
As of September 15, 2026, all construction activities associated with this project have been completed.
The project will repave US 19 from south of Tampa Road to south of Live Oak Street in Pinellas County.
This project also includes the installation of upgraded ADA features and facilities as needed.
Construction is anticipated to be complete in fall 2026.