• Emergency Generator Replacement – State Account – C916
Scope of Work – Replace and reposition emergency generator. Approved budget - $300,000.
Working with Division of Engineering and Contract Administration to select engineering firm for phase A design.
• Install Signage and Lighting on Pedway – State Account – C95V
Scope of Work – Design and install signage and lighting on the pedway that crosses US 60. Approved budget - $80,000.
Working with Division of Engineering and Contract Administration to select design and installation firm.
• Energy Performance Savings Contract – State Account – N/A
Scope of Work – Develop project to reduce energy costs and improve efficiency. Project is funded from guaranteed savings.
Presentations from interested firms scheduled for September 12th. Firms will be evaluated by a joint team of Kentucky State University staff and Division of Engineering and Contract Administration staff.
Estimated completion date – December 2020
Privately Funded Projects
• Transition to Synthetic Athletic Field – State Account – N/A
Scope of Work – Install a synthetic athletic field.
Working with stakeholders to develop budget and potential cost sharing for the project. Estimated completion – April 1, 2019