Scope of Work – Replace section of Jordan Warehouse roof. Project closed August 2018. Further repairs and or replacement will be determined as part of overall campus roof evaluation.
Scope of Work – Remediate mold throughout the building and repair mechanical systems. Approved project budget - $900,000; Expended to date - $45,000. Mold remediation complete – July 2018. Mechanical repairs are more extensive than anticipated. CMTA Engineers are completing phase A design. Updated project budget will be submitted for Board approval at the September 6, 2018 meeting. Project Completion - 5%.
Scope of Work – Develop campus master plan. Approved budget - $325,000. Working with Division of Engineering and Contract Administration to select architect. Review team for selection of Architect has been assigned.
Scope of Work – Develop cost estimate and initial design to convert Shauntee Hall to Nursing Education facility. Approved budget - $30,000.
Working with Division of Engineering and Contract Administration to select architect.
Scope of Work – Evaluate issues and develop repair estimates for campus buildings with roof problems. Evaluate alternative designs. Approved Budget - $50,000 Working with Division of Engineering and Contract Administration to select architect.