| Heritage | ● Not located within a Conservation Area, however it is adjacent to the southern boundary of the Castlefield Conservation Area that runs along the A56.
● There are 15 heritage assets within 250m of the with the closest being the Grade II listed Electricity Junction Box in Castlefield canal basin approx. 30m away |
|---|
| Flood Risk and Drainage | ● Flood Zone 1 (low risk) |
|---|
| Transport and Access | Proximity to key destinations:
● 5m walk to Deansgate Train Station / Metrolink (0.2 miles) to the north
● 11 mins walk to Oxford Road (0.5 miles)
● 11 mins walk to city centre core / St Peter's Square (0.5 mile)
● 11 mins walk to Oxford Road Train Station (0.5 mile)
● 21 mins walk to UoM Main Campus (1 mile)
● 12 mins walk to the MMU campus (0.6 miles)
Accessibility:
● Closest convenience store (Sainsburys) located 4 minute walk (300m) east
● Restaurants, bars and other leisure uses located within Deansgate a 5 – 10 mins walk east but also along Deansgate and Castlefield both within 5-10 minutes' walk.
● The main retail and leisure core of the City Centre is located to the north of the site, within a 15 minute walk or 5 minute tram journey.
● Adjacent to Deansgate for quick vehicular access into city centre and ring road (Mancunian Way).
● Number of bus stops are located in close proximity to the site on both sides of the A56 as well as along Whitworth Street to the north of the site.
● The site benefits from good levels of nearby recreational cycle routes along the Bridgewater Canal.
● First Street is located 500m to the east of the site and provides a mix of commercial, residential, retail and leisure use.
● The neighbourhood of Hulme is located further south of the site along with the Birley Fields Manchester Metropolitan University (MMU) Campus. The campus is a 15-minute walk from the site (0.7 miles).
● Other MMU faculty buildings within close proximity to the site include the Manchester Business School, the MMU Library and the Manchester School of Art, all of which are a 15 – 20-minute walk. |
|---|
| Ground Conditions | ● The approved ground conditions report concludes there is a moderate /low potential for the site to be contaminated due to its previous industrial use, however this will be remediated prior to redevelopment. |
|---|
| Ecology | ● No ecological designations on site.
● No Tree Preservation Orders.
● No trees on site |
|---|
| Noise | ● Approved noise report concludes no impacts in regard to noise and that the development will comply with MCC standards |
|---|
| Air Quality | ● This site is located within the Manchester Air Quality Management Area |
|---|
| Green and Blue Infrastructure | ● The MCC Green and Blue Infrastructure Strategy identifies the following opportunities:
● Enhanced blue corridors create safe, attractive green routes for a walkable/cyclable city, health benefits and accessible 'lunch hour' green space for city workers |
|---|
| Daylight and Sunlight | ● The approved daylight / sunlight study concludes no significant impacts. |
|---|
| Townscape and Visual Impact | ● The approved TVIA study concludes no significant impacts. |
|---|
| Wind Microclimate | ● Identified incidents of off-site significant adverse wind safety impacts. The safety issues identified would have serious potential consequences for the general public – uncertainty around inability to suitably mitigate.
● LPA decision notice (dated 4 June 2021): "failed to demonstrate that the mitigation measures put forward are capable of implementation and no alternatives have been put forward".
● The appeal decision to grant planning permission comes with a planning condition (Condition 3) which requires details of mitigation measures to provide a safe and comfortable wind environment in and around the site for pedestrians and cyclists Associated with this condition is the need to provide a viability assessment for any associated tree planting that is required in this regard, within the public realm. |
|---|
| Capacity (indicative) | ● 534 PBSA bedspaces as per planning permission 129406/FO/2021. |
|---|
| Infrastructure Capacity (limitations) | ● Servicing and refuse collections will be made from the lay-by-on Deansgate South, with building management responsible for moving bins out to the street in a phased manner, maintaining thoroughfare along the pedestrian footpath at all times. |
|---|