| Site | Ownership | Current Status | Capacity (bedspaces) | Current Deliverability & Defensibility Rating (Red/Amber/Green) | Potential Academic Opening Year (Sept) | Key findings and recommendation |
|---|
| 7) Great Marlborough Street | Student Castle Investments LLP | Planning Approved – no start on site | 853 | Green | 2027 | • Planning permission was granted in 2021; however, that decision had until very recently been the subject of a legal challenge via Judicial Review. The case was dismissed in January 2023 and therefore it is now assumed that the scheme will come forward over a 4-5 year period. |
|---|
| 8) ID Manchester | UoM (/ Bruntwood SciTech) | Pre-Planning | -N/A | Red | N/A | • We understand that PBSA is not currently identified by the landowner and JV as a desired component of the innovation district. |
|---|
| 9) IQ Echo Street | IQ Student | Planning Permission Validated May 2023 - awaiting determination | 1,224 | Amber | 2026 | • Planning permission (118267/FO/2017) previously granted for 242 PBSA bedspaces, supported with co-living units. Scheme stalled and new proposals submitted (see below).
• Planning application submitted (136874/FO/2023) by the same applicant / operator as the previous permission for a full PBSA development with, capturing the units previously allocated for co-living.
• Timescales for delivery subject to ensuring target determination. Current timescales a 3 year construction period with the applicant aiming to target completion to allow occupation for the 26/27 academic year.
• Our recommendation would be for MCC officers to continue to work with the developer, local Members and local residents in order to seek a positive resolution and grant of planning permission for this scheme. |
|---|