ACTION ITEM:

Approval of Budget Increase for the Chandler Hall Renovation Project

FACTS:

  • Chandler Hall, built in 1939, spans 28,000 square feet and houses 115 students.
  • It has undergone two renovations, the most recent occurring in 1993.
  • The building suffers from significant deferred site maintenance, outdated systems, and moisture issues, as well as failing or deteriorating architectural components (both interior and exterior).
  • This project will include:
  • Upgrades to the mechanical, electrical, and plumbing systems
  • Architectural improvements (e.g., low-maintenance flooring, building envelope repairs)
  • The repurposing of underutilized space, potentially increasing bed capacity
  • Major construction is scheduled to begin in December 2024, with completion anticipated by November 2025.

BUDGETARY IMPLICATIONS:

  • The project was previously approved with a $9,970,000 budget during the September 2024 Board meeting.
  • As design efforts progressed, additional building envelope and HVAC issues were identified, thus increasing the estimated cost by $300,000.
  • The total projected budget is now $10,270,000.
  • The additional $300,000 will come from the University's 2022–2024 state bond-funded asset preservation funds, consisting of $260,869.57 in state bond funds and $39,130.43 in University matching funds.

RECOMMENDATION:

President Koffi C. Akakpo recommends that the Board of Regents approve the budget increase for the Chandler Hall Renovation Project.

MOTION:

Approve the budget increase for the Chandler Hall Renovation Project.