Environmental Impact Statement Block 20101, Lots 29 & 30 Jackson Township, Ocean County, New Jersey
6.0 REQUIRED LICENSES, PERMITS, AND APPROVALS
January 9, 2026 Page 25 of 28
Table 3: Approvals Status
Granting AuthorityLicense, Permit or ApprovalStatus
Jackson Township Planning BoardPreliminary and Final Site Plan ApprovalSubject of this application
Ocean County Planning BoardPreliminary and Final Site Plan ApprovalConcurrent Application
Ocean County Soil Conservation DistrictSoil Erosion and Sediment Control PlanConcurrent Application
NJDEPFreshwater Wetlands Letter of Interpretation – Line VerificationSubmitted - Pending Approval (PI # 1511-06-0003.2)
7.0 ALTERNATIVES ANALYSIS
The following alternatives were evaluated in demonstrating that the proposed location and design of the proposed development:
8.0 ADVERSE ENVIRONMENTAL IMPACTS THAT CANNOT BE AVOIDED
No Development Alternative: Leaving the site in its existing condition would avoid short term construction impacts but would not advance municipal housing objectives, efficient use of land already served by public infrastructure, implementation of modern stormwater controls, or orderly infill development consistent with surrounding residential subdivisions.
Alternate Location: Relocating the project to another site would likely require expansion of infrastructure, encounter greater environmental constraints, and reduce compatibility with established residential development patterns, offering no meaningful environmental or planning advantage over the subject site.
Reduction of Scope: Reducing the number of lots would not materially decrease environmental impacts because roadway access, utilities, stormwater infrastructure, and grading would still be required, while potentially impairing project feasibility and efficient land utilization.
A number of undesirable environmental impacts are unavoidable during and after construction:
A permanent displacement of the surficial geologic deposits in the form of underlying soils will occur because of additional grading, foundation and basin construction and other earth disturbances;