===== PAGE 1 ===== ## PRO JECT O VERVIEW Project Limits: From Elam Road to Lake June Road, City of Balch Springs, Dallas County Project IDs: 0918-47-313 & 0918-47-436 Project Length: Approximately 1.12 miles of Hickory Tree Road ## Cost Breakdown: Cost Breakdown: Design: $5.2 million ROW: $3.1 million Construction: $22 million Utility: $3 million Right of Way: The project would require acquisition of 2.3 acres of right-of-way, 0.3 acre of permanent easement, and 2.3 acres of temporary easement ## Contact: Chris Dyser – cdyser@balchspringstx.gov City of Balch Springs, Business & Capital Senior Director 13503 Alexander Road Balch Springs, TX 75181 972-286-4477 x.1310/1610 ## ESTIMATED PROJECT M ILESTO NES Feb 2026 Public Meeting Feb 2026 Apr 2026 Environmental Clearance
Image
Mar 2027 May 2028 Aug 2030 Finish ROW Acquisition & Utility Relocation Begin Construction End Construction