PRO JECT O VERVIEW

Project Limits: From Elam Road to Lake June Road, City of Balch Springs, Dallas County

Project IDs: 0918-47-313 & 0918-47-436

Project Length: Approximately 1.12 miles of Hickory Tree Road

Cost Breakdown: Design: $5.2 million ROW: $3.1 million Construction: $22 million Utility: $3 million

Cost Breakdown:

Right of Way: The project would require acquisition of 2.3 acres of right-of-way, 0.3 acre of permanent easement, and 2.3 acres of temporary easement

Contact:

Chris Dyser – cdyser@balchspringstx.gov City of Balch Springs, Business & Capital Senior Director 13503 Alexander Road Balch Springs, TX 75181 972-286-4477 x.1310/1610

ESTIMATED PROJECT M ILESTO NES

Finish ROW Acquisition & Utility Relocation Begin Construction End Construction

Aug 2030

May 2028

Mar 2027

Feb 2026 Apr 2026 Environmental Clearance

Feb 2026 Public Meeting

Hickory Tree Road Reconstruction from Elam Road to Lake June F