Project Limits: From Elam Road to Lake June Road, City of Balch Springs, Dallas County
Project IDs: 0918-47-313 & 0918-47-436
Project Length: Approximately 1.12 miles of Hickory Tree Road
Cost Breakdown:
Design: $5.2 million
ROW: $3.1 million
Construction: $22 million
Utility: $3 million
Right of Way: The project would require acquisition of 2.3 acres of right-of-way, 0.3 acre of permanent easement, and 2.3 acres of temporary easement
Chris Dyser – cdyser@balchspringstx.gov
City of Balch Springs, Business & Capital Senior Director
13503 Alexander Road
Balch Springs, TX 75181
972-286-4477 x.1310/1610
Aug 2030
May 2028
Mar 2027
Feb 2026
Apr 2026
Environmental Clearance
Feb 2026
Public Meeting
Hickory Tree Road Reconstruction from Elam Road to Lake June F