Sarasota/Manatee US 41 Corridor Mobility and Safety Study (CMASS) Project Summary
4. Timeline
Table 1 provides a timeline of the work completed during the US 41 CMASS project.
Table 1: Timeline of Work Completed
EventDate
Notice to ProceedFeb 2022
Communication Plan & Online Questionnaire Development & FinalizationMay 2022 - May 2023
CMASS & Connecting Communities BrandingFeb - Mar 2022
Project Working Group Meetings (in coordination with Sarasota/Manatee MPO US 41 Concept of Operations meetings)Feb - May 2022
Storyboard DevelopmentApr 2022
Website CreationMay 2022
Agency Update Presentations
Sarasota Manatee MPO BPTAC Presentation4/19/2022
Sarasota Manatee MPO CAN Presentation5/9/2022
Sarasota Manatee MPO TAC Presentation5/9/2022
Sarasota Manatee MPO Board Presentation5/23/2022
Manatee BoCC Presentation6/7/2022
Bradenton City Council Presentation6/15/2022
Palmetto City Council Presentation6/27/2022
Transect Map of Existing ConditionsNov 2022
Develop Goals & ObjectivesJan 2023
Develop Measures of EffectivenessJan 2023
One-on-One Stakeholder Meetings
Bradenton Area Convention & Visitors Bureau1/17/2023
New College of Florida1/18/2023
Sarasota Manatee Airport Authority1/19/2023
Greater Sarasota Chamber of Commerce1/20/2023
University of South Florida Sarasota-Manatee1/20/2023
Manatee NAACP1/24/2023
Manasota Black Chamber of Commerce2/1/2023
Bradenton Area Economic Council2/3/2023
Data Collection
Efficient Transportation Decision Making (ETDM) Environmental Screening Tool (EST) Area of Interest (AOI)Nov 2021
Previous Studies & Planned ProjectsFeb - Mar 2022
Existing Conditions Data CollectionFeb 2022 - Nov 2023
Crash Data Collection and AnalysisFeb 2022
Traffic CountsMay - July 2023
Bike & Pedestrian FeaturesAug - Oct 2023