Information Technology Report: July 2008 – March 2009
Information Technology is actively working toward the completion of projects that will enhance and improve operational efficiency and customer service and will reduce cost for the overall university. The department is also strengthening its internal processes through reorganizing by functional areas to better serve the needs of the students, faculty and staff.
| Project | Components | Complete |
|---|
| Enterprise Resource Plan Implementation | Discovery Sessions held
Students
Human Resources
Finance will be scheduled for later
Technical scheduled for week of April 20th
Overall Project Plan Development | 50%
75% complete |
|---|
| Blackboard Transaction System | Door Access
Residence Halls
Hathaway
Meal Plans
Bookstore Purchases
Laundry – Residence Halls
Vending (Snack and Beverage Machines)
Print Services (Residence Halls)
Community System Activation | 90%
100%
100%
100%
95%
0%
50%
In Progress |
|---|
| Exterior Wireless Access Points | Exterior
Planned Installations
Installed Units
Percent Complete
Interior
Planned Installations
Installed Units
Percent Complete | 30
20
66%
295
155
52% |
|---|
| Alumni E-mail | Application Software Installation | 100% |
|---|
| Emergency Notification System | Web Site – Registration Capability
Registered Users – as of Jan. 7
Registered Users – as of April 1 | 100%
469
641 (172 new registrants) |
|---|
| Surveillance Camera Installation | Exterior
Planned Installations
Installed Units
Percent Complete
Interior
Planned Installations
Installed Units
Percent Complete | 20
10 unchanged
50%
120
42
35% |
|---|
| Digital Signage | Planned Installations
Installed Units
Percent Complete | 33
20
60% |
|---|
| Online Donations | Application Software Development | In progress |
|---|
18