Information Technology Report: July 2009 – September 2009
Information Technology is actively working toward the completion of projects that will enhance and improve operational efficiency and customer service and will reduce cost for the overall university. The department is also strengthening its internal processes through reorganizing by functional areas to better serve the needs of the students, faculty and staff.
Project
Enterprise Resource Plan Implementation
| Components | Complete |
|---|
| Teams have been created for the Banner Project: | The hardware will be installed at the beginning of November |
| Student
Finance
Human Resources
Financial Aid
Technical | The Banner software will be installed Mid-November |
| All of the teams are actively engaged in meeting with SunGard consultants for data discovery activities and mapping/conversion | The first data conversion on the Banner system will be completed in January 2010. |
| A campus-wide communications plan is being developed | The teams will be engaged in data cleanup and learning the Banner system |
| An informational Web site has been established that will contain Banner Project updates. | The current go live dates are: |
| Finance and Human Resources – Jan. 2011 |
| Financial Aid – Feb. 2011 |
| Student – March 2011 |