PROJECTGOALRESULTS / COMMENTS
14Jordan Building and Warehouse Roof Replacement 2012$229,500Partial funding of $90,000 provided. Design beginning in July
15Carroll ASB Roof Replacement Phase I 2012$349,000No funding; will be placed on next year's schedule
16Cooperative Extension Building 2012$196,290No funding; will be placed on next year's schedule
17Betty White additional Parking$99,980Project being advertised for bids
18Brick Retaining Wall and Fence for Betty White Parking$106,452Bids received for retaining wall. Construction to begin in July
19McCullin Additional Parking$57,245Under construction. Completion in July
20J Parking Lot Paving$67,000Under construction
21Fill and Retaining Wall for J Lot by McCullin$65,000Under construction
22President's Dining Room$25,000on hold
23Vehicle Purchase from Surplus$13,000One vehicle purchased from State surplus in April 2012; a second vehicle is being purchased in July
Auxiliary Services
24Russell Court Roof Replacement 2012$90,318Design to begin in July
25Atwood Research Bldg. Interior Renovation 2012$2,000,000On hold
26Office Building Center for Sustainable Farms and Fam 2012$1,200,000On hold
27New Entry Road at Farm$68,000Completed in July
28Work with State Finance Cabinet to Increase Small Purchase Authority Limit from $40,000 to $350,000Final information provided
29Kentucky Hall BathroomsModernize bathroomsRescheduled for Summer 2013
30Hillcrest BathroomsRepair and UpdateUnder construction
31Flower Pots for Kentucky Chandler SidewalkAestheticsVendor found for large round plastic pots
32Exum Interior SignsAestheticsIn progress
33New Women's Softball Field at Jones FieldTitle IX complianceLocation is being mapped out
34Bradford Hall Little Theater Renovation to Large Seminar ClassroomProjects on bid
35Bradford Hall FurnitureUpdate classroom furnitureSpecs and bid documents submitted to purchasing June 1
36Hillcrest Interior RenovationsRepairs and updatesIn progress
37Pulley and Ring System at ExumFor event setups
38Campus TurfAestheticsIn progress