PROJECTGOALRESULTS / COMMENTS
Projects in Progress
1Entrance GatehouseControlled access to campusProject under construction with projected October 12 completion
$560,000
2Parking Lot ExpansionMore parking for students/faculty/staff1 lot completed December 2011; two lots under construction
$83,000 Capital Planning
3Russell Court Interior RenovationsModernized ApartmentsDesign specs from Moody Nolan received in June
$1,000,000 Auxiliary Services
4Privatized Housing RFPNew Student HousingFirm selection completed. Project on hold
$20 million private developer/ KSU Foundation
52010 HUD HBCU GrantReceive grant to buy property in Hill Top neighborhoodKSU was not awarded grant
$450,000 (requested budget for next year)
6Redesign President's SuiteImprove safety and enlarge conference roomDesign completed in May 2011; project is being advertised for bid in July
$19,000 Capital Planning
7Construct New Building and Facilities to Service University NeedsOne project under construction
8Determine Renovations of Buildings for New Functions and Upgrades of Building SystemsOne renovation project has been established for construction in summer and fall 2012
9Identify and Address Deferred Maintenance IssuesSix new deferred maintenance projects identified and in progress
10Initiate An Annual Deferred Maintenance PlanAnnual deferred maintenance plan is in operation
11Construct New Student Residential HousingThe university is currently holding on constructing new residential housing
12ADA Access for HillcrestReceived direction to proceed from Board of Regents committee in May 2012
13Alumni Stadium Office Roof Replacement 2012 $306,000$ 306,000Design for new roof to begin in July
Capital Planning, Construction and Facility Operations Board of Regents Report 2011-2012