PROJECTGoalAssigned DateSTATUSComments
39Jordan Building and Warehouse Roof Replacement 2012 $229,500229,50005/01/12
40Carroll ASB Roof Replacement Phase I 2012 $349,000349,00005/01/12
41Cooperative Extension Building 2012 $196,290196,29005/01/12
42Old Federal Building additional funding $60,00060,00005/01/12COMPComplete
43Betty White Additional Parking99,98005/01/12Redesign complete
44Brick Retaining Wall and Fence Betty White Parking106,45204/15/12Redesign complete
45McCullin Additional Parking57,24505/01/12
46J Parking Lot Paving67,00005/01/12Construction under way
47Fill and Retaining Wall for J Lot by McCullin65,00005/01/12Construction under way
48Additional Funds for Bradford Hall Seating9,56705/01/12COMPComplete