PROJECTGoalAssigned DateSTATUSComments
1Entrance GatehouseControlled Access to Campus09/01/10Project under construction - Oct. 12 completion
Anticipated Funding Source
$220,000 Auxiliary Services
$200,000 Capital Planning
$140,000 Title III Infrastructure, Electronic Security
2Repair Concrete Steps & SidewalksSafe pedestrian paths08/01/10Complete
$150,000 Capital PlanningComplete
3Erosion Control at Motor PoolControl of water runoff07/01/10Complete
$15,000 Capital PlanningComplete
4Flood Damage Repair at Old Federal BuildingRestore building05/05/10Complete
5Extend Storm Pipe at Ash PitRoute storm water around ash pit05/27/10Complete
$5,000 Maintenance OperationsComplete
6Repair Roof of Old Federal BuildingStop damage from leaking roof07/01/10Complete
$13,000 Capital PlanningComplete
7Access Control for Governmental Services CenterInstall Blackboard electronic card readers05/01/10Complete
$20,000 GSC Maintenance ServiceComplete
8Mills Lane Farm - Center for Sustainable Farms & FamiliesNew Facility03/27/09Complete
$4,800,000 USDAComplete
9Aquaculture Production Technology LaboratoryNew Facility08/15/10Complete

Capital Construction Project Report April 27, 2012