Capital Planning, Construction and Facility Operations April 26, 2013

ID Project Name Duration Start Finish 2012 2013 2014 2015

Jul Sep Nov Jan Mar May Jul Sept Nov Jan Mar

1 Russell Court Interior Renovation 760 days 03/01/13 03/31/15

2 Alumni Stadium Office Building Roof Replacement 2013 91 days 03/01/13 05/31/13

3 Jordan Warehouse Roof Replacement 2013 91 days 03/01/13 05/31/13

4 Russell Court Roof Replacement 2013 91 days 03/01/13 05/31/13

5 Betty White Additional Parking 303 days 08/01/12 05/31/13

6 New Parking Lot by McCullin 242 days 10/01/12 05/31/13

7 New Women's Softball Field at Jones Field 91 days 06/01/13 08/31/13

8 Bradford Hall Little Theater Renovation to Large Seminar Classroom 91 days 07/01/13 09/30/13

9 Cheaney Memorial Plaza 153 days 05/01/13 10/31/13

10 Pedestrian Bridge over US 60 274 days 04/01/13 12/31/13

11 Feasibility of Constructing a Centralized Mail Hub In Student Center Basement 136 days 04/01/13 08/15/13

12 Refurbish Exum Gym Basketball Court 40 days 03/07/13 04/16/13

Projects
In Progress25
On Hold6
Total31
Completed since July 1, 201219
Canceled2