Information Technology
May 11, 2011
Information technology is evolving quickly. KSU's Office of Information Technology is developing active plans to anticipate and leverage IT trends and contribute to the university's strategic plan and top goals.
Information Technology is actively working toward the completion of several projects that will enhance and improve operational efficiency, customer service and reduce cost for the overall university. The department is also strengthening its internal processes by reorganizing by functional area to better serve the needs of students, faculty and staff.
Project
Banner ERP Implementation
| Components | Complete |
|---|
| Phase 1 | |
|---|
| Discovery and Hardware Installation | 100% |
|---|
| Phase 2 | |
|---|
| Conversion R1 | 100% |
|---|
| Data verification and validation | 100% |
|---|
| Data clean-up | 100% |
|---|
| Banner testing & problem resolution | 100% |
|---|
| Phase 2.5 | |
|---|
| Conversion R1.5 | 100% |
|---|
| Data verification and validation | 100% |
|---|
| Data clean-up | 100% |
|---|
| Banner testing & problem resolution | 100% |
|---|
| Phase 3 | |
|---|
| Conversion R2 | 100% |
|---|
| Data verification and validation | 100% |
|---|
| Data clean-up | 100% |
|---|
| Banner testing & problem resolution | 100% |
|---|
| Phase 4 | |
|---|
| Integration testing (classroom pilot) | 100% |
|---|
| Phase 5 | |
|---|
| Pre-Prod creation for production | 100% |
|---|
| Banner PROD delivery to KSU Dec. 6 | 100% |
|---|
| Campus Banner training begun (FI and HR) | 100% |
|---|
| Phase 6 | |
|---|
| Campus Banner Training (FI, HR, FA, ST) | 100% |
|---|
| Finance GO LIVE (Jan. 2011) | 100% |
|---|
| Human Resources GO LIVE (Jan 2011) | 100% |
|---|
| Financial Aid GO LIVE (Feb 2011) | 100% |
|---|
| Student GO LIVE (Mar 2011) | 90% |
|---|
| Accounts Receivable GO LIVE (July 2011) | 70% |
|---|