Capital Planning, Construction and Facility Operations July 27, 2013
ID Project Name Duration Start Finish 2012 2013 2014 2015
Jul Sep Nov Jan Mar May Jul Sept Nov Jan Mar May Jul Sept Nov Jan Mar
1 Russell Court Interior Renovation 607 days 08/01/13 03/31/15
2 Alumni Stadium Office Building Roof Replacement 2013 100 days 07/01/13 11/16/13
3 Jordan Warehouse Roof Replacement 2013 87 days 07/01/13 10/31/13
4 Russell Court Roof Replacement 2013 87 days 07/01/13 10/31/13
5 Betty White Additional Parking 333 days 08/01/12 06/30/13
6 New Parking Lot by McCullin 274 days 10/01/12 07/01/13
7 New Women's Softball Field at Jones Field 91 days 08/01/13 10/31/13
8 Bradford Hall Little Theater Renovation to Large Seminar Classroom 91 days 07/01/13 09/30/13
9 Cheaney Memorial Plaza 183 days 08/01/13 01/31/14
10 Pedestrian Bridge over US 60 364 days 04/01/13 03/31/14
11 Feasibility of Constructing a Centralized Mail Hub in Student Center Basement 136 days 04/01/13 08/15/14
12 Refurbish Exum Gym Basketball Court 40 days 03/07/13 04/16/13
13 Hillcrest Kitchen Renovation 83 days 05/01/13 07/23/13
14 Student Support Services Offices 60 days 07/01/13 08/30/13
Projects
| In Progress | 27 |
|---|---|
| On Hold | 6 |
| Total | 33 |
| Completed since July 1, 2012 | 19 |
| Canceled | 2 |