9 Reroof Atwood Research Non-leaking roof Feb-11 Dec-11 PIP Under Construction

10 Cheaney Plaza Fundraising bricks and plaques Aug-10 Aug-12 PIP Design Phase

$500,000 Private donations

11 Feasibility of constructing a centralized mail hub in Student Center Basement Streamline mail pickup Aug-10 Jun-11 PNIP On hold

$ Auxiliary Services

$150 Capital Planning

12 Campus benches Replace old benches around campus Aug-10 Oct-11 PIP Benches being installed Oct11

$10,000 Capital Planning

13 New seating in Bradford Hall Large Auditorium New seating in large auditorium Aug-10 Aug-11 PIP Seating being fabricated

$120,000 Capital Planning

14 Scoreboard as Football Stadium New Scoreboard Feb-11 Aug-11 PIP Under Construction

15 (IT) Intercom System at Football Stadium New Intercom System at Alumni Stadium Feb-11 Aug-11 PIP Under Construction

16 Parking lot expansion More parking for students/faculty/staff Jan-11 Oct-11 PIP Construction to begin in October

$83,000 Capital Planning

17 Russell Court interior Renovations Modernized Apartments Jun-10 Aug-12 PIP

$1,000,000 Auxiliary Services

18 Privatized Housing RFP New Student Housing Nov-09 Aug-12 PIP Developer Selected

$20M Private Developer/ KSU Foundation