Project In Progress (PIP)
Complete (COM) Projected
Project Not in Progress (PNIP) Assigned Completion
Project Goal Date Date Status Comments
1 Entrance Gatehouse Controlled Access to Campus Sep-10 Oct-11 PIP In Design
2 Repair Concrete Steps & Sidewalks Safe Pedestrian paths Aug-10 Jun-11 PIP 90 % complete. Bell Gym steps remaining
$150,000 Capital Planning
3 Erosion Control at Motor pool Control of water runoff Jul-10 Aug-11 PIP In Progress
$15,000 Capital Planning
4 Flood Damage Repair at Old Federal Building Restore Building May-10 Jun-10 COM Complete
$5,000 Maintenance Operations
6 Repair Roof of Old Federal Building Stop damage from leaking roof Jul-10 Aug-10 COM Complete
$13,000 Capital Planning
7 Access Control for Governmental Services Center Install Blackboard electronic card readers May-10 Aug-11 PIP Received bid of $650 from contractor
$20,000 GSC Maintenance Service
9 Aquaculture Production Technology Laboratory New Facility Aug-10 Aug-11 PIP Construction in progress
$1,700,000 CPE
$500,000 Federal Funding
10 Rosenwald Ctr for Families & Children New Facility Jun-10 Aug-11 PIP Construction in progress
$2,400,000
Capital Construction Project Report - July 22, 2011