Capital Planning, Construction and Facility Operations

October 25, 2013

ID Project Name Duration Start Finish 2012 2013 2014 2015 2016

Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul

1 Russell Court Interior Renovation 760 days 02/01/14 12/29/16

2 Alumni Stadium Office Building Roof Replacement 2013 91 days 11/01/13 03/07/14

3 Jordan Warehouse Roof Replacement 2013 175 days 03/01/13 11/01/13

4 Russell Court Roof Replacement 2013 91 days 03/01/13 07/05/13

5 Betty White Additional Parking 303 days 08/01/12 05/31/13

6 New Parking Lot by McCullin Hall 242 days 10/01/12 05/31/13

7 New Women's Softball Field at Jones Field 91 days 03/01/14 07/04/14

8 Bradford Hall Little Theater Renovation to Large Seminar Classroom 91 days 01/01/14 05/07/14

9 Cheaney Memorial Plaza 362 days 01/11/13 05/31/14

10 Pedestrian Bridge over US 60 274 days 09/01/13 09/17/14

11 Feasibility of Constructing a Centralized Mail Hub in Student Center Basement 136 days 04/01/13 10/07/13

12 Refurbish Exum Gym Basketball Court 40 days 03/07/13 04/16/13

13 Atwood Research Interior Renovation 420 days 10/01/13 12/31/14

14 Interpretive Center KSU Downtown Annex 300 days 10/01/13 08/31/14

15 Repair Cooperative Extension Building Roof 240 Days 10/01/13 06/30/14

In Progress 21 On Hold 6

Completed 22 Canceled 2

Total 51