![]() | Overall Status | Status |
|---|---|---|
| 1 Projected Go Live Date: January 2, 2017 | ![]() | |
Project on Time? | The project is at risk of not meeting the projected go live date due to the number of critical activities that need to be completed prior to that date. The Executive Team is also working through some performance issues with the parallel team. The Executive Team has informed ERP Analysts that its parallel team is not meeting its contractual obligation to act on behalf of KSU. The ERP Analysts team is responding to KSU's notice of deficiencies and working with KSU to resolve the problems. | ![]() |
Is the project within Budget | Project is within the budget. | ![]() |
| Legend | ||
Track Potential Risk(s), Needs Attention | Potential Adverse Impact to Scope, Schedule or Budget | Not Stated |