TCS KSU Parallel TeamThe team consists of the TCS functional staff. The team will bring in depth knowledge and expertise while serving as the KSU end user.
KSU General User TeamThe team consists of the KSU functional users. This team attends training and completes post-training evaluation to ensure proficiency.
Oracle & Third Party Application OwnersProvide necessary input and support to the TCS Implementation and KSU Project Executive teams for relevant integrations and other technical items.
Key Upcoming Activities:
Evaluation of relationship with TCS
Review and signoff on the following:
Project Charter
Detailed Project Plan
Risk Register
Mitigation Plan
Responsibility Assignment Matrix
Completion of detailed business processes
Completion of business requirements document
Completion of first demonstration
Tentative and High-level Project Schedule as Proposed by TCS
Project Item
Project Planning
Requirements Gathering and Detailed Design
Data Extraction, Cleansing, and Migration
Training
Build and Testing
Campus Solutions and Cloud ERP Go-Live December 2016
Post Implementation Efforts and Transition
[2]
Timeline
October 2015 - December 2015
November 2015 – March 2016
March 2016 - December 2016
March 2016 - October 2016
April 2016 – December 2016
January 2017 - March 2017