KENTUCKY STATE UNIVERSITY Regular Meeting of the Board of Regents External Relations and Development Committee January 24, 2014 9:00 am to 10:00 am Board Room – Academic Services Building Frankfort, Kentucky

CAPITAL PLANNING, CONSTRUCTION AND FACILITY OPERATIONS REPORT

ID Project Name Duration Start Finish 2012 2013 2014 2015 2016

Apr Jul

1 Russell Court Interior Renovation 760 days 02/01/14 12/29/16

2 Alumni Stadium Office Building Roof Replacement 2013 91 days 11/01/13 03/07/14

3 Jordan Warehouse Roof Replacement 2013 176 days 03/01/13 11/01/13

4 Russell Court Roof Replacement 2013 91 days 03/01/13 07/05/13

5 Betty White Additional Parking 218 days 08/01/12 05/31/13

6 New Parking Lot by McCullin 175 days 10/01/12 05/31/13

7 Bradford Hall Little Theater Renovation to Large Seminar Classroom 91 days 01/01/14 05/07/14

8 Cheaney Memorial Plaza 362 days 01/11/13 05/31/14

9 Pedestrian Bridge over US 60 274 days 09/01/13 09/17/14

10 Refurbish Exum Gym Basketball Court 29 days 03/07/13 04/16/13

11 Atwood Research Interior Renovation 327 days 10/01/13 12/31/14

12 Interpretive Center KSU Downtown Annex 240 days 10/01/13 08/31/14

13 Repair Cooperative Extension Building Roof 195 Days 10/01/13 06/30/14

14 Intersection Realignment Langford and Douglas Ave 336 Days 08/01/14 08/31/15

15 Privatized Student Housing 392 Days 12/01/13 05/31/15

50 ProjectsOn Hold8
In Progress15Canceled2
Completed25Total50