CAPITAL PLANNING, CONSTRUCTION AND FACILITY OPERATIONS REPORT

ID Project Name Duration Start Finish 2012 2013 2014 2015 2016

Apr Jul Oct Apr Jul Oct Apr Jul Oct Apr Jul Oct Apr Jul Oct

1 Russell Court Interior Renovation 760 days 02/01/14 12/29/16

2 Alumni Stadium Office Building Roof Replacement 2013 91 days 11/01/13 03/07/14

3 Jordan Warehouse Roof Replacement 2013 176 days 03/01/13 11/01/13

4 Russell Court Roof Replacement 2013 91 days 03/01/13 07/05/13

5 Betty White Additional Parking 218 days 08/01/12 05/31/13

6 New Parking Lot by McCullin 175 days 10/01/12 05/31/13

7 Bradford Hall Little Theater Renovation to Large Seminar Classroom 91 days 01/01/14 05/07/14

8 Cheaney Memorial Plaza 362 days 01/11/13 05/31/14

9 Pedestrian Bridge over US 60 274 days 09/01/13 09/17/14

10 Refurbish Exum Gym Basketball Court 29 days 03/07/13 04/16/13

11 Atwood Research Interior Renovation 327 days 10/01/13 12/31/14

12 Interpretive Center KSU Downtown Annex 240 days 10/01/13 08/31/14

13 Repair Cooperative Extension Building Roof 195 Days 10/01/13 06/30/14

14 Intersection Realignment Langford and Douglas Ave 336 Days 08/01/14 08/31/15

15 Privatized Student Housing 392 Days 12/01/13 05/31/15

50 Projects In Progress Completed

50 Projects8
In Progress2
Com-50

15 25

On Hold8
Canceled2
Total50