Capital Projects Update
| ID | Project Name | Start | Finish | Percentage of Completion |
|---|---|---|---|---|
| 1 | Alumni Stadium Office Building Roof Replacement | 11/1/2013 | 7/31/2014 | 100% |
| 2 | Cheaney Legacy Plaza | 1/11/13 | 10/31/2014 | 95% |
| 3 | Pedestrian Bridge over US 60 | 3/26/2014 | 4/13/2015 | 10% |
| 4 | Interpretive Center KSU Downtown Annex | 3/26/2014 | 2/24/2015 | 0% |
| 5 | Intersection Realignment Langford and Douglas Ave. | 3/26/2014 | 4/23/2015 | 10% |
| 6 | Utility Relocation for Pedestrian Bridge | 4/1/2014 | 1/31/2015 | 40% |
13