Cooperative Extension Bldg. Roof Replacement/Repair 2012
State Account No.: C66Q
Fund Source: Federal Funds
Appropriation: $270,000.00
Cash Balance: $-156,499.54
Architectural Firm: G. Scott & Associates, Architects, Frankfort, Kentucky
Actual Construction Cost total with changes: $235,250.00
Start: 01/09/2017 Substantial: 06/30/2017 Final Completion: 07/30/2017 Construction time will be extended.
Construction Prime Contractor: The Bri-Den Co., Inc., Ashland, Kentucky
Modular Units for Agricultural Research
State Account No.: C8CD
Fund Source: Land Grant
Appropriation: $573,473.00
Cash Balance: $526,738.50
Architectural Firm: Greystone Architects, Frankfort, Kentucky
Actual Construction Cost total with changes: $561,500.00
Bid Date 6/8/2017
Construction Prime Contractor: Jacobs Group, Louisville, Kentucky
The bid is $61,127.00 over budget. This amount is within the budgeted construction contingency; it is not within the funding authorized for Land Grant. Additional funds must be found or the project cancelled or reduced in scope. Half of the trailers could potentially be installed. If another site location is required then the project will require redesign.
Land Grant is searching for leased lab space and plans to cancel this project.
Renovate Atwood Ag Research Building
State Account No.: C751
Fund Source: Federal Funds
Appropriation: $12,368,000.00
Architectural Firm: Omni Architects, Lexington, Kentucky
Design Fees Allotment: $369,420.00
Phase A Construction Estimate: $5,257,308.00
Design is pending approval of funding for architectural design fee from USDA
This project initially started out as state account number C6EX with a $2,000,000 appropriation in 2013. $400,000 were transferred to the state for design services from KSU operating funds. $30,579 was expended by the state and $369,421 was returned when the state closed account C6Ex
No funds have been transferred to state account C751
Emergency Roof Repairs - Exum HPER Center
State Account No.: C8HZ