State Account No.: C756
o Fund Source: State Bonds authorized in Fiscal Year 2014-2015
○ Appropriation: $10,400,000.00
Cash Balance: $-621,387.50
Mechanical Engineer Prime Firm: CMTA Consulting Engineers, Prospect, Kentucky
Actual Construction Cost total with changes: $6,600,107.00
○ Start: 06/13/2016 Substantial: 08/01/2017 Final Completion: 09/01/2017
○ Construction Prime Contractor: Hussung Mechanical Contractors, Louisville, KY
o Phase I: Status: The new installation of three (3) hot water boilers in the Blazer Library that supply heat to the North side of the campus. These boilers are online and completed.
Phase II: Status: The new installation of three (3) hot water boilers in the Bell Gym that supply heat to the East side and part of the South side of the campus. These boilers are online and completed.
Phase III: Status: The new installation of one (1) steam boiler in the central plant that supply heat to the West side of the campus. This boiler is scheduled to be online and completed on Wednesday, November 22, 2017.
State Account No.: C66Q
o Fund Source: Federal Funds
○ Appropriation: $270,000.00