State Account No.: C756
o Fund Source: State Bonds authorized in Fiscal Year 2014-2015
○ Appropriation: $10,400,000.00
Cash Balance: $-621,387.50
Mechanical Engineer Prime Firm: CMTA Consulting Engineers, Prospect, Kentucky
Actual Construction Cost total with changes: $6,600,107.00
○ Start: 06/13/2016 Substantial: 08/01/2017 Final Completion: 09/01/2017
○ Construction Prime Contractor: Hussung Mechanical Contractors, Louisville, KY
o Phase I: Status: The new installation of three (3) hot water boilers in the Blazer Library that supply heat to the North side of the campus. These boilers are online and completed.
Phase II: Status: The new installation of three (3) hot water boilers in the Bell Gym that supply heat to the East side and part of the South side of the campus. These boilers are online and completed.
Phase III: Status: The new installation of one (1) steam boiler in the central plant that supply heat to the West side of the campus. This boiler is scheduled to be online and completed on Wednesday, November 22, 2017.
Pedestrian Bridge across US60
State Account No.: 151064
o Fund Source: KY Transportation Cabinet, Road Funds FY 2013
O Appropriation: $8,200,000.00
Civil Engineer Prime Firm: Palmer Engineering, Winchester, Kentucky
Actual Construction Cost total with changes: $5,100,000.00
Start: 10/27/2015 Final Completion: 10/11/2017. Project is behind schedule. Will need additional work crews to meet the new scheduled completion date
○ Construction Prime Contractor: Hall Contracting of Kentucky Inc., Louisville, Kentucky
Utility Relocation by FPB Construction Cost: $691,342.93 is compete
Johnson Control is scheduled to install 14 security cameras and two (2) emergency phones in the elevator tower along the pedestrian way. The estimated cost for this project is $61,986.00. This cost is not included in the original construction.
Status: Work is currently in progress.
Cooperative Extension Bldg. Roof Replacement/Repair 2012
State Account No.: C66Q
o Fund Source: Federal Funds
○ Appropriation: $270,000.00