2018-2020 Kentucky Branch Budget Capital Budget Request: Capital Construction Project Record All dollar amounts rounded to next $1000
Capital Budget Record CBR-02
Branch: Executive Branch
Cabinet: Postsecondary Education
Agency: Postsecondary Education Institutions
Appropriation: Kentucky State University
Project Title: Expand Campus Communications Infrastructure
KBUD Project Number: 435U18C006
PriorityCapital Budget RequestSix-Year Capital Plan 2018-20
Cabinet:
Agency:66
PROJECT DOCUMENTATION
Location (County): Franklin
Reauthorization - Regular Capital Project: Is this a currently authorized project which is being requested for reauthorization and/or
additional funding? NO
If (Yes, Additional Funding), provide the following information:
eMars Project Number (Agency, Fund):
New Total Project Cost: $2,354,000
Capital Project Type:
Project Description
The purpose of this project is to continue to improve upon the University's communication infrastructure with installation of new underground conduit network for redundant connectivity capability. This project will construct a conduit path from Julian Carroll ASB to Hathaway Hall and Bradford Hall plus another path from Julian Carroll ASB to Aquaculture compound.
PROJECT BUDGET
Has this project been reviewed by the Department for Facilities and Support Services?
Fund SourceRequested FY 2017-18Requested FY 2018-19Requested FY 2019-20Requested Total
Bond Funds02,354,00002,354,000
Total Funds02,354,00002,354,000
Cost Elements
Site Survey/Preparation016,000016,000
Project Design0215,0000215,000
Contingency Expense0214,0000214,000
Construction Costs01,909,00001,909,000
Total Costs02,354,00002,354,000
Completion Date: 09 / 2020
IMPACT ON OPERATING BUDGETFY1 AmountFY2 AmountFY3 AmountFY4 AmountFY5 Amount
Fund Source
00000
Total Costs00000
Cost Element
00000
Total Expenditures00000