Roof Needs from 2015 Winter, Updated March 2015

# Buildings

Building Name Total Bldg. Roof Area Replacement / Repairs Construction 2015 Dollars Contingency Total Cost Comments

Square Feet Square Feet Estimated 20% Estimated

Small & Quick Repairs 1.40 /Sq Ft 6.05 $/Sq Ft Shingle

Alumni House 3,546 100 $ 140 Shingle Roof

Carver Hall Annex 8,076 344 $ 481 Roof section F, 1 Issue / Need

Motor Pool 11,020 10,820 $ 15,120

QEP HOUSE 840 300 $ 1,814 Shingle Roof

Rosenwald Police Center 9,800 9,800 $ 13,695

$ -

Small & Quick Total 42,782 30,864 $ 44,526 6

  • Small & Quick Total 42,782 30,864 $ 44,526

Must Do, Leaking $ 22.96 $/Sq Ft $ 6.05 $/Sq Ft Shingle

Hume Hall 9,500 9,500 $ 13,276

Cooperative Ext Bld 13,086 13,086 $ 160,000 $ 40,000 $ 200,000 Architect Finishing Design

Baseball Restroom 1,500 1,500 $ 34,440 $ 8,610 $ 43,050

Betty White 6,177 6,177 $ 141,824 $ 35,456 $ 177,280 Insulation Wet

Jordan Maint. 5,458 5,458 $ 125,316 $ 31,329 $ 156,645

Must Do Total 26,221 26,221 $ 752,543

Stadium Press Box 1,900 0 - - $ - Rebuild Structure

Should Do $ 22.96 $/Sq Ft $ 6.05 $/Sq Ft Shingle

  • Must Do Total 26,221 26,221 $ 752,543

- - $ -

Carroll Academic Serv Bld 43,200 43,200 $ 991,872 $ 247,968 $1,239,840

Exum Center 91,250 91,100 $ 2,091,656 $ 522,914 $2,614,570

Kentucky Hall 17,200 17,200 $ 104,025 $ 26,006 $ 130,031 Shingle Roof

McCullin Hall 10,400 10,400 $ 62,899 $ 15,725 $ 78,623 Shingle Roof

Should Do Total 196,650 173,900 4,407,464 5

  • Should Do Total 196,650 173,900 4,407,464

Blazer Library, Roof B & F 34,600 12,000 $ 275,520 $ 68,880 $ 344,400

[58]