Task_Name Duration Start Finish Cost March April May June July Aug
3/29 4/5 4/12 4/19 4/26 5/3 5/10 5/17 5/24 5/31 6/7 6/14 6/21 6/28 7/5 7/12 7/19 7/26
ELECTRIC 97 3/27/2015 7/2/2015 $33,653
CHANDLER 3 5/11/2015 5/13/2015 $1,900
Summer inspection & repairs 3 5/11/2015 5/13/2015 $1,900
KENTUCKY 8 5/18/2015 5/27/2015 $1,900
Summer inspection & repairs 8 5/18/2015 5/27/2015 $1,900
HUNTER 6 5/28/2015 6/4/2015 $2,037
Bathroom lighting 6 5/28/2015 6/4/2015 $2,037
COMBS 6 6/5/2015 6/12/2015 $2,003
Summer inspection & repairs 6 6/5/2015 6/12/2015 $2,003
MCCULLIN 8 6/15/2015 6/24/2015 $1,900
Summer inspection & repairs 8 6/15/2015 6/24/2015 $1,900
WHITNEY YOUNG 69 3/27/2015 7/1/2015 $7,900
Summer inspection & repairs 5 6/25/2015 7/1/2015 $1,900
Innovation center 1 3/27/2015 3/27/2015 $6,000
THE HALLS 1 7/2/2015 7/2/2015 $4,041
Summer inspection & repairs 1 7/2/2015 7/2/2015 $4,041
ASB 21 3/27/2015 4/24/2015 $2,932
Bathroom lighting upgrade 21 3/27/2015 4/24/2015 $2,932
HUME 1 3/27/2015 3/27/2015 $1,220
Front ground floodlight replace 1 3/27/2015 3/27/2015 $1,220
JACKSON 1 5/15/2015 5/15/2015 $1,220
Front ground floodlight replace 1 5/15/2015 5/15/2015 $1,220
HUNTER 6 5/28/2015 6/4/2015 $1,400
Bathroom overhead fixture replacement 6 5/28/2015 6/4/2015 $1,400
6-buildings 9 5/29/2015 6/10/2015 $700
Mobile charging stations 9 5/29/2015 6/10/2015 $700
ALL CAMPUS 13 6/10/2015 6/26/2015 $4,000
Exterior light repairs 13 6/10/2015 6/26/2015 $4,000
BRADFORD 7 5/21/2015 5/29/2015 $500
Stairwell lighting 7 5/21/2015 5/29/2015 $500
Grounds 56 5/15/2015 7/31/2015 $1,200
Cut dead trees down campus wide 25 5/15/2015 6/18/2015 $1,200
JONES FIELD 35 6/15/2015 7/31/2015 $0
Start up irrigation system for football stadium, Jones Practice & Baseball 35 6/15/2015 7/31/2015 $0