| Task_Name | Duration | Start | Finish | Cost | March | April | May | June | July |
|---|
| CARPENTRY | 140 | 3/27/15 | 8/14/15 | $180,930 | 3/15 | 3/22 | 3/29 | 4/5 | 4/12 | 4/19 | 4/26 | 5/3 | 5/10 | 5/17 | 5/24 | 5/31 | 6/7 | 6/14 | 6/21 | 6/28 | 7/5 | 7/12 | 7/19 | 7/26 | 8/2 | 8/9 | 8/16 | | | | | |
|---|
| COMBS | 10 | 5/15/15 | 5/28/15 | $10,250 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace all broken ceiling tile in the hallways on each floor | 10 | 5/15/15 | 5/28/15 | $2,500 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Repair hole in wall of 4th floor restroom | 10 | 5/15/15 | 5/28/15 | $150 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace Ceiling panel in lobby area | 10 | 5/15/15 | 5/28/15 | $200 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace soap dish in showers all floors | 10 | 5/15/15 | 5/28/15 | $400 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Repair furniture in all rooms | 10 | 5/15/15 | 5/28/15 | $4,000 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace broken Blinds in all rooms | 10 | 5/15/15 | 5/28/15 | $1,500 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace transition strip in all rooms. | 10 | 5/15/15 | 5/28/15 | $1,000 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace Broken glass in all fire stations | 10 | 5/15/15 | 5/28/15 | $500 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| HUNTER | 54 | 3/27/15 | 6/10/15 | $32,200 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace glass in middle stairwell | 3 | 5/22/15 | 5/26/15 | $500 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace missing door room number on each floor | 10 | 5/28/15 | 6/10/15 | $500 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| HVAC Leak in lobby repair | 1 | 3/27/15 | 3/27/15 | $0 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Repaint ceiling on each floor | 10 | 5/28/15 | 6/10/15 | $250 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| 1st floor, replace metal sheet panel | 10 | 5/28/15 | 6/10/15 | $150 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Shower bench restoration | 10 | 5/28/15 | 6/10/15 | $300 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Carpet replacement Project | 3 | 5/28/15 | 6/1/15 | $30,000 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Laundry room ceiling tile replacement | 10 | 5/28/15 | 6/10/15 | $500 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| MCCULLIN | 15 | 6/3/15 | 6/23/15 | $7,830 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace all broken tiles on all floors | 10 | 6/10/15 | 6/23/15 | $160 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| 2nd floor, Replace blinds in study room | 10 | 6/10/15 | 6/23/15 | $150 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Vending machine room floor tile replacement | 10 | 6/10/15 | 6/23/15 | $320 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace all missing transition strip all floors | 6 | 6/3/15 | 6/10/15 | $2,000 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Pipe insulation in basement | 7 | 6/10/15 | 6/18/15 | $1,500 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Window repairs, replace Glass and window lever | 4 | 6/18/15 | 6/23/15 | $1,200 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace all damage ceiling tiles | 10 | 6/10/15 | 6/23/15 | $2,500 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| KENTUCKY | 20 | 6/23/15 | 7/20/15 | $7,100 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Repaint Laundry room/ Kitchen on each floor | 10 | 6/23/15 | 7/6/15 | $400 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Furniture repair all rooms- bed, dresser, desk, chair, wd | 10 | 6/23/15 | 7/6/15 | $4,000 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Window repair | 5 | 7/14/15 | 7/20/15 | $1,200 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace all damage blinds | 10 | 6/23/15 | 7/6/15 | $1,500 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| WHITNEY YOUNG | 5 | 7/6/15 | 7/10/15 | $6,500 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace blinds | 5 | 7/6/15 | 7/10/15 | $2,500 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Repair furniture all floor /all rooms | 5 | 7/6/15 | 7/10/15 | $4,000 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| CHANDLER | 10 | 7/10/15 | 7/23/15 | $2,950 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace damage ceiling tile in lobby | 10 | 7/10/15 | 7/23/15 | $250 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Repair all base board in hallway all floors | 10 | 7/10/15 | 7/23/15 | $1,200 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Replace all broken blinds in building | 10 | 7/10/15 | 7/23/15 | $1,500 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| STUDENT CTR | 5 | 7/23/15 | 7/29/15 | $2,000 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Student center Entry repair/repaint | 5 | 7/23/15 | 7/29/15 | $2,000 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| ALL DORMS | 16 | 6/23/15 | 7/14/15 | $39,600 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| All resident dorms Mattress replacement | 14 | 6/23/15 | 7/10/15 | $35,000 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Campus Screen replacement | 3 | 7/10/15 | 7/14/15 | $4,600 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| EXUM | 4 | 7/28/15 | 7/31/15 | $2,500 | | | | | | | | [52] | | | | | | | | | | | | | | | | | | | | |
|---|
| Exum floor tiles main entrance | 4 | 7/28/15 | 7/31/15 | $2,500 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| BLAZER LIBRARY | 11 | 7/31/15 | 8/14/15 | $70,000 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|
| Library carpet replacement project | 11 | 7/31/15 | 8/14/15 | $70,000 | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---|