Task_Name Duration Start Finish Cost April May June July Aug Sept

4/5 4/12 4/19 4/26 5/3 5/10 5/17 5/24 5/31 6/7 6/14 6/21 6/28 7/5 7/12 7/19 7/26 8/2 8/9 8/16 8/23 8/30 9/6 9/13 9/20 9/27

Alumni House 4 6/1/15 6/5/15 $ 140

Carver Hall Annex 10 5/15/15 5/25/15 $ 481

Hume Hall 4 5/4/15 5/8/15 $ 13,276

Motor Pool 2 4/6/15 4/8/15 $ 15,120

QEP HOUSE 2 4/1/15 4/3/15 $ 1,814

Rosenwald Police Center 4 4/20/15 4/24/15 $ 13,695

Small & Quick Total $ 44,526

Cooperative Ext Bld 81 7/1/15 9/20/15 $ 200,000

Baseball Restroom 4 4/20/15 4/24/15 $ 43,050

Betty White 11 9/7/15 9/18/15 $ 177,280

Jordan Maint. 11 9/7/15 9/18/15 $ 156,645

Blazer Library, Roof B & F 11 9/7/15 9/18/15 $ 344,400

Carroll Academic Serv Bld 11 9/8/15 9/19/15 $ 1,239,840

Exum Center 11 9/9/15 9/20/15 $ 2,614,570

Kentucky Hall 11 9/10/15 9/21/15 $ 130,031

Should Do Total $ 4,407,464

Bell Gym 11 9/7/15 9/18/15 $ 334,173

HILLCREST 11 9/7/15 9/18/15 $ 34,156

Must Do Total $ 576,975

McCullin Hall 11 9/11/15 9/22/15 $ 78,623

MARYLAND WAREHOUSE 11 9/7/15 9/18/15 $ 66,929

Long Term Replacement Total $ 435,258

Total Roof Needs 174 4/1/15 9/22/15 $ 5,464,222