Task_Name Duration Start Finish Cost 5/3 5/10 5/17 5/24 5/31 6/7 6/14 6/21 6/28 7/5 7/12
UTILITY TUNNELS 47 5/15/15 7/1/15 $5,000
Inspect the condensate pumps and tanks 1 5/15/15 5/16/15 $0
Drain all traps and leave the valves open 1 5/15/15 5/16/15 $0
Clean out all trash 1 5/15/15 5/16/15 $0
Replace the lights that are out 1 5/15/15 5/16/15 $500
Replace any insulation that is damaged 1 7/1/15 7/2/15 $1,000
Inspect all trap piping, replace valves and pipes as needed 1 6/29/15 6/30/15 $3,500
Inspect the exhaust fans and leave them turned on during shut down period 1 5/18/15 5/19/15 $0
AIR COMPRESSORS 1 7/6/15 7/7/15 $1,500
Service air compressors and have ready for start-up 1 7/6/15 7/7/15 $1,500
COAL SYSTEM 5 5/15/15 5/20/15 $1,300
Clean up all coal that is left on in the hopper outside chute, belt conveyor and in the elevator buckets and tank 4 5/15/15 5/19/15 $0
Inspect all working parts throughout the system, repair or replace what is needed 1 5/20/15 5/21/15 $1,300